Nichols Boulevard Pavement Rehabilitation Project

Nichols Boulevard Pavement Rehabilitation Project

The City of Longview has contracted with Advanced Excavating Specialists to construct
improvements along Nichols Boulevard from Washington Way to Louisiana Street.
Construction on the project began May 6, 2019.

Asphalt pavement work was completed July 27, 2019. Remaining work on the project includes
curb ramp work, striping, and signal work. This work is scheduled to last through August 30,
2019.

Intermittent closures at the Louisiana St, Hemlock St. and Washington Way intersections will
be required to complete striping on August 15, 16, and 17, 2019. Vehicle traffic will be flagged
through the intersections for this work. Expect delays of up to 15 minutes.
All dates are subject to change bases on construction progress and weather.

In order to avoid delays, motorists are encouraged to use alternate routes.